R.Baker & Son
R. Baker Logo
R.Baker & Son Home Page R.Baker & Son Safety Page R.Baker & Son News R.Baker & Son Pictures R.Baker & Son Contact
Press Room
Turn Key Services
Rigging Contractors
Dismantling Contractors
Selective Demolition
Total Demolition Contractor
Interior Demolition
Wrecking / Razing Contractors
Plant Decommissioning Contractors
Environmental Services
Investment Recovery
Plant Relocation Services Contractor
Trucking / Warehousing
All Projects
gray space
quick quote
extend navigation
R Baker and Son Press Releases
Wed September 1, 2010, 8:03 am
Sept 2010 Rigging and Demolition Newsletter Available...
(read more)
Thu August 26, 2010, 3:34 pm
R. Baker & Son Ranked #1 Demolition- Wrecking Contractor...
(read more)
Fri August 20, 2010, 8:59 am
Why We Believe R. Baker & Son Is Your Best Industrial...
(read more)
Mon August 2, 2010, 11:02 am
NDA Publishes High Reach Demolition Safety Document...
(read more)
RSS Feed

 

 

Selective Demolition Contractors Services by R. Baker & SonSelective Demolition Contractor Services Thoughout the US, Canad
Merck & Co.

R. Baker & Son was contracted by Merck & Co. to perform an extremely complex and intricate deconstruction and selective demolition project.  The scope consisted of the decommissioning and dismantling of three bulk production plants.  It was critical that there were no disruption of active plant services which ran through and near buildings to be demolished.

A special program was used to identify services required to remain in place, design new supports where needed, and implement, system-by system and area-by-area, dismantling plans.  This demonstrated to our client our complete understanding of what had to be done before any work was started.

The equipment in the building was decommissioned, cleaned, and rigged for resale on the used equipment market.  Operational systems and services were re-supported, and the arduous task of manual selective dismantling was performed.  Once the equipment was fully decommissioned, it was rigged out of the building through cooordinated access areas; the building was then entirely dismantled.  During the project, we ensured that DI water, nitrogen, electrical systems, and other critical services supporting other buildings were unaffected.  The project was executed exactly as required by Merck.
 

 