All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Rigging Setting the Final Pieces of Process Equipment

Rigging Setting the Final Pieces of Process Equipment

A large, ongoing pharmaceutical project was facing a dilemma. With most work progressing smoothly and on-schedule, equipment for one very important process area would not be arriving onsite until the very end of the project. R. Baker & Son and the construction manager came up with an ingenious plan for rigging the equipment into the facility without interrupting the flow of the project. 

R. Baker & Son had rigged and set in place various mechanical equipment including chillers, cooling towers, air handlers, heat exchangers, tanks, air compressors, and plumbing skids. Some of the process equipment arrived at the job site next and was routed through the corridors and into the process suites following a detailed rigging and routing plan developed early in the project. Process equipment included large isolators, tanks, servo lifts, filling lines and several large platforms. 

The process area in question was to include a two-story fluid bed, a granulator, and process air handling unit with control panel. All of the pieces were being fabricated and factory acceptance-tested before they were shipped from overseas. Because of the massive size of the equipment, R. Baker would not be able to bring it through the building, so it was decided that it would be rigged vertically through an exactly-plotted and measured opening in the roof directly into the process suite onto pre-erected platforms where they would be mounted with precision. 

The final process equipment arrived three weeks from the completion date. All areas had been substantially finished, and finishing touches and punch list items were being completed. With a clear window of weather forecast, the temporary roof above the process suite was removed along with a section of ceiling fifteen feet below. The process air handling unit was rigged in on-end to fit through the opening, then turned to its horizontal position and set on its mechanical platform. Next, two Hoffman enclosure control panels were rigged onto the mechanical platform. The 1-ton, 8-ft. tall granulator came next, followed by the two-story vertical fluid bed weighing three tons, its feet mounted directly onto the awaiting stainless steel platform. 

Once the equipment had been set in place, the ceiling and roof openings were closed and sealed. Final electrical and mechanical interconnects were completed on the process equipment and air balancing was performed. The building was completed on time, and the project received its Certificate of Occupancy as scheduled.

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a  Service-Disabled Veteran-Owned Business (SDVOB)  in business since 1935, is a premier specialized contractor operating in the United States, Canada and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

http://rbaker.com

Full News Archive

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

University Hospital NY - Renovation Project
Hospital Renovation Project

A large university hospital in New York had several buildings on campus. The central building, a 75,000 sq. ft. four-story structure with a mechanical penthouse was the first to be erected in 1944,...
Demolition Contractor: Earning & Keeping Our Reputation
Demolition Contractor: Earning and Keeping Our Great Reputation

A demolition contractor’s reputation is everything, and what can take decades to build can be lost very quickly if great care is not taken. Customers have specific overall expectations, most...
Demolition Project Goes Underground
Demolition Project Goes Underground

A 175,000 square-foot OTC R&D and production building, constructed in the early 1960s, was undergoing complete interior demolition to be repurposed as a pilot facility. The demolition schedule...
Copper Recycling Offsets Dismantling Project Costs
Copper Recycling Offsets Dismantling Project Costs

A large electrical-mechanical contractor hired R. Baker & Son to perform all of the electrical equipment dismantling and mechanical equipment removal at an old vitamin production facility...
CUP Multi-Phase Selective Demolition Project: Demo by Color
CUP Multi-Phase Selective Demolition Project: Demo by Color

An aging central utility plant serving a large northern New Jersey hospital was due for complete renovation, including the replacement of almost all equipment including boilers, chillers, cooling...
Rigging Safety Guidelines - Industrial Services
Rigging Safety Guidelines

Safety is paramount at R. Baker & Son, which is why we strictly observe all rigging safety regulations, guidelines and procedures on every lift we do. Guidelines for rigging safety: Inspect...
R. Baker Salvages Fixtures for Reuse on Plant Consolidation Project
R. Baker Salvages Fixtures for Reuse on Plant Consolidation

A longtime client approached R. Baker & Son with a plant relocation project in which operations at several partially-occupied buildings were to be moved to a single 200,000 sq. ft. building...
Planning for Rigging & Demo Projects
Safety Planning for Rigging and Demolition Projects

When performing a rigging or demolition project, falling materials, fall hazards, unstable structures, and a variety of other hazards can pose serious risks to both workers and the general public, so...