Demo Project Bid Leveling Sheets Can Make All the Difference

use of a checklist during the bidding process

One of the keys to a successful demolition or selective demolition project outcome is the development and use of a checklist during the bidding process known as the leveling sheet. The leveling sheet defines the scope of the project in minute detail, spelling out exactly what is included or excluded in each demolition contractor’s proposal and effectively leveling the bids for a fair comparison. Without a leveling sheet, items can go unidentified, leading to an array of problems, change orders, delays, finger-pointing, and all-around hard feelings between client and contractor.

Leveling sheet specifications on a demolition project might include:

Will demolition equipment used be battery operated or diesel?

Environmental hazards such as asbestos, lead paint, or old tanks – will they be remediated, and how?

Is the project union or non-union, and what are the working hours? Will there be second and third shifts?

Will dust and vibration be limited to specific hours?

Asset recovery – are there items of value such as copper wire or salvageable equipment that can offset project costs?

Will the demolition contractor use subcontractors to perform electrical, plumbing or mechanical aspects of their project?

Does the demolition project include specific safety items such as ISNetworld, VPPP, HAZWOPER, etc.?

Using a leveling sheet to identify what is included or excluded on any demolition or select demolition project can ensure that equipment and services are purchased wholesale from the outset, not at retail prices after the fact. Doing your homework can save a lot of money and streamline your demolition project.

R. Baker & Son - All Industrial Service
1 Globe Court
Red Bank, NJ 07701
http://www.rbaker.com

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

 Sweeping Compounds for Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates
Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates

Demolition is a dirty job that can produce layers of dirt, dust, and silica that settle on floors and other flat surfaces. There are various techniques and equipment such as misting cannons,...
Rigging equipment, rigging hook, NYC
Auger and Centrifuge Rigging Project

An existing customer called R. Baker & Son needing assistance with rigging equipment duringtheir facility’s annual cleaning and maintenance project. The manufacturing plant was set up for...
Cooling Tower Dismantling Project
University Cooling Tower Dismantling Project

A large Staten Island mechanical contractor contacted R. Baker & Son to remove a 1,000-ton cooling tower at a university to make way for a new high-efficiency tower and filtration system. The...
Danger sign for rigging, dismantling & demolition site
Rigging, Dismantling & Demolition Project Safety

Safety is the number one priority on every R. Baker & Son project, from dismantling, rigging, and demolition, to plant decommissioning, plant relocation, and environmental services. Safeguards...
construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...
Pre-construction, tablet on table of demolition contractor
Preconstruction Services or Precon

The goal on every construction, renovation or demolition project is to have experienced, reputable contractors bid the project competitively. Preconstruction services, often referred to as precon,...
Asset Recovery: Refurbished Parts and Equipment in High Demand
Asset Recovery: Refurbished Parts and Equipment in High Demand

With supply chain shortages and inflation continuing into 2022, the demand for reconditioned parts and equipment is on the rise. Investment recovery, also known as asset recovery, of aged equipment...
Generator Replacement
Weekend Standby Generator Replacement

A large laboratory and office complex needed to replace an existing standby generator with a new, larger 2000 kW unit with associated automatic transfer switches and day tank. The owner needed the...