R.Baker & Son
R. Baker Logo
R.Baker & Son Home Page R.Baker & Son Safety Page R.Baker & Son News R.Baker & Son Pictures R.Baker & Son Contact
Press Room
Turn Key Services
Rigging Contractors
Dismantling Contractors
Selective Demolition
Total Demolition Contractor
Interior Demolition
Wrecking / Razing Contractors
Plant Decommissioning Contractors
Environmental Services
Investment Recovery
Plant Relocation Services Contractor
Trucking / Warehousing
All Projects
gray space
quick quote
extend navigation
R Baker and Son Press Releases
Wed September 1, 2010, 8:03 am
Sept 2010 Rigging and Demolition Newsletter Available...
(read more)
Thu August 26, 2010, 3:34 pm
R. Baker & Son Ranked #1 Demolition- Wrecking Contractor...
(read more)
Fri August 20, 2010, 8:59 am
Why We Believe R. Baker & Son Is Your Best Industrial...
(read more)
Mon August 2, 2010, 11:02 am
NDA Publishes High Reach Demolition Safety Document...
(read more)
RSS Feed

 

 

Tubine Dismantlement, Rigging and Moving by R. Baker and SonDismantlement, Rigging Services and Machinery Moving by R. Baker
Yankee Atomic

R. Baker & Son performed the dismantling and removal of the secondary site of the Yankee Atomic's Rowe facility. 

The project consisted of of a 185 MW steam turbine generator and ancillary equipment including a high pressure turbine rotor and blading, an installed low pressure turbine rotor, the generator itself, the rotating and static exciters, the main transformer and the No. 1 station service transformer along with other ancillary equipment such as 100-ton overhead bridge crane.

Much of the turbine dismantling was executed by using the plant's existing 100-ton bridge crane.  Many of the unit's components exceeded the crane's capacity and required engineered lifts or partial dismantlement.  Removal of the 115-ton turbine cover also required an engineered lift.  The cover was then cut into four sections for removal.

Lead abatement procedures were required before all burning and cutting.  All loads were radiation-tested before leaving the site and strict load limits were followed during transporation off-site.

All employees on-site were required to complete a 40-hour safety training course conducted by the Nuclear Regulatory Commission.  They were required to wear radiation detection badges at all times during the project.

 
      Valid HTML 4.01 Transitional  
R. Baker & Son Copyright
R. Baker & Son Copyright
novametis