All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Interior Demo: Mid-Project Changes Save Time and Money

Interior Demolition - Wet Saw

Discovering an opportunity for substantial cost savings during a project in progress is always a welcome surprise, which was the case on a warehouse renovation in which R. Baker & Son was tasked with performing the   of the 200,000 sq. ft. building. The building was to become a manufacturing plant with 10,000 square feet of offices occupying one corner and heavy mechanical areas throughout the facility. 

Phase one of the interior demolition project was fairly standard. After careful planning and coordination of utility shutoff, everything within the building’s four outer walls and roof were removed using equipment that included forklifts, loaders, and skid steers brought in through existing loading dock doors. R. Baker & Son also handled reclamation and resale of an existing generator and multiple transfer switches to help offset some of the demolition costs. 

The second phase of demolition was saw-cutting and removal of approximately 50,000 sq. ft. of the concrete floor slab to accommodate the new plant’s underground sanitary and process plumbing. It was during this time that it became clear that, with some careful planning and cutting of an addition 4,000 sq. ft. of slab by the Baker Team, much of the overhead electrical conduit and cable tray could be relocated below ground fairly easily, saving a considerable amount of money in labor and material. Not having racks of conduit suspended from the ceiling or cable tray with miscellaneous steel supports would also result in a much cleaner, more aesthetically-pleasing installation. 

R. Baker & Son worked closely with plumbing and electrical contractors throughout the BIM coordination process for precisely relocating, trenching and backfilling all pipe and conduit. These changes resulted in savings of $112,000 and four weeks were shaved from the overall master schedule. With a tight budget, aggressive schedule and cost overruns in other areas of the project, this was music to the owners’ ears.

Full News Archive

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Chemical Bursting: Concrete Demolition
Chemical Bursting: The Silent Revolution in Concrete Demolition

While traditional concrete demolition often relies on hydraulic breakers, pneumatic drills, saw cutting, and explosives, some projects demand more subtle approaches. Chemical bursting, also known as...
Demolition and Rigging: A Half Century of Safety Innovation
Demolition and Rigging: A Half Century of Safety Innovation

Safety stands as the cornerstone of everything we do at R Baker and Son's demolition and rigging operations. Those of us with decades of experience in the field understand the importance of...
Toolbox Talks, R. Baker & Son Demolition Crew
Safety Through Dialogue: The Critical Role of Toolbox Talks

Toolbox talks are a cornerstone of effective company safety programs. These informal safety meetings, typically held on job sites before work begins, focus on specific safety topics and are designed...
Safety in Construction
The Critical Importance of Safety Investment in Construction

In the construction industry, and especially our industry, investing in safety is not just a regulatory requirement—it's a strategic decision that yields numerous benefits. A comprehensive...
Demolition company discussing pricing
Understanding the Difference Between Lowest Price and Best Price

In purchasing services, particularly in contracting, it's crucial to understand that the "lowest price" rarely equates to the "best price." Smart purchasing involves looking...
R. Baker BIM Laser Scans for Demolition Project
Accelerated Project Timelines with R. Baker BIM Laser Scans

R. Baker was awarded a large demolition project in an existing 130k sq/ft laboratory facility to make way for a new modern lab facility. Our client had presented us with a very aggressive demolition...
Positive Safety Habits - Industrial Rigging Equipment
Building a Safer Environment: The Power of Positive Safety Habits

Safety is contagious, much like many other human behaviors. We are naturally inclined to be influenced by positive examples set by others. When a driver buckles up, passengers often follow suit. This...
Rigging and Replacing Old Equipment - Boilers, Chilling Towers
R. Baker Seamlessly Rigging and Replacing Old Equipment

Recently, a large hospital in central New Jersey successfully completed extensive HVAC and electrical changes. These changes, which were a significant undertaking, included replacing two chillers and...