Refinery Selective Demolition Project
R. Baker was recently involved in a large selective demolition project at a petroleum refinery/research center located in northern New Jersey. The project demoliton, to make way for a new exhaust system and new lab hoods throughout the facility was a complex one. Complicated by the facility's fortress-like construction, with rebar-reinforced, 12-inch-thick floors, walls, ceiling, and roof. Baker crews performed demolition, coring, cutting, rigging, and assembly. Removal of the equipment was the first, and easiest stage of the project.
During this enabling phase R. Baker & Son crew members worked closely with the client to determine which pieces of equipment and fixtures would be removed and when, so lab users would have advance knowledge to temporarily work around the missing equipment. When the selective demolition was completed, the more difficult tasks began. Floors and walls were x-rayed to determine where electrical conduit was located. X-rays were performed at night to minimize radiation risks to building occupants.
The images required careful study to differentiate between rebar and conduit throughout the floor. Once electrical conduits were identified, they were traced to the nearest electrical panel, and circuits were isolated and rerouted so the floors could be cored. These circular passageways ranged from eight inches to eighteen inches in diameter throughout the facility. Because the coring machine was water cooled, conduits had to be plugged with clay to prevent water from flowing down into the labs through conduit openings. Some areas could not be cored and had to be jackhammered to expose the conduits and make way for control wiring risers.
The entire effort was coordinated with a structural engineer and the HVAC designer. New ductwork, fire dampers, and controls were installed within the openings throughout the building. Large new exhaust fans and plenums were rigged onto the roof, and new lab fume hoods were assembled and installed in all labs. The new lab exhaust system worked in conjunction with the 100% outside air system which provided 105,000 CFM of air throughout the building.
Upon completion of the new ventilation system, new pre-fabricated casework was installed where needed for lab experiments.
R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553
http://www.rbaker.com
Decommissioning
Demolition Contractors in New York
- Surgical Demolition Project - Turbine Generator - New York (NYC)
- Fulton Fish Market Dismantling / Demolition Project NY - New York, NY
- R. Baker & Son Curtain Wall Projects - New York, NY
- Port Mobil Tank Farm & Builidng Demolition - Staten Island, NY
- World Trade Center Transportation Hub Project - WTC NYC
- Restoration of the United Nations - NYC
- Kings County Hospital - Tri State Area
- JFK'S American Airlines Terminal Demolition - New York
Environmental Services
Investment Recovery
Plant Relocation
Selective Demolition
Trucking / Warehousing
Curtain Wall
Demolition Contractors in New Jersey
- Demolition Project Makes Way for New Renaissance High School - Camden, NJ
- Demolition For New Transmission Station - Harrison, NJ
- Controlled Demolition: Asbestos Abatement
- Con Edison Close Proximity Demolition
- Merck Demolition Project - NJ - New Jersey
- Turnkey Demolition Project - Barceloneta, Puerto Rico
Dismantling
Interior Demolition
Plant and Machinery Movers
Rigging
- United Nations: Moving The World's Treasures - Manhattan, NYC
- Facility Of The Year Award (FOYA) for Pharmadule Project - New Jersey
- Rigging Fire Truck at 9/11 Memorial Ceremony - Manhattan, NYC
- Domino Sugar: A Slice of History - Brooklyn, NY
- USS Intrepid - Manhattan, Pier 86, NYC
- Petrochemical Plant: Rigging & Dismantling - New Jersey
- Colgate Palmolive - Jersey City, NJ
- Dismantling and Rigging, Plant Relocation Project - New Jersey
- Complex Rigging in Pharmaceutical Plant - NJ