All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Interior Demolition: Epoxy Floor Removal

Interior Demolition: Epoxy Floor Removal Project

R. Baker & Son was contracted to perform interior demolition at a New Jersey pharmaceuticals manufacturing plant. Originally built in 1948, the second floor of the two-story building had served for decades as a 62-room vivarium, and the now-vacant area was to be repurposed as open offices with high ceilings and laboratories with downflow booths.
 
The first demolition task required to prepare for renovation was the removal of all of the old terracotta block and concrete walls throughout the 25,500 sq. ft. area. Removal of the walls revealed sixty-two individual 12’ x 12’ areas with thick, pitched, troweled-on epoxy floors with drains in the center of the rooms, as well as seven corridors. Removal of the epoxy floors down to the concrete below would require multiple passes by five Blastrac BMS-280 ride-on floor scrapers. Four National 550 floor scrapers were utilized in areas that couldn’t be accessed by the ride-on machines. Other equipment used during the wall and floor demolition included three Bobcats and two pneumatic hammers.
 
Following wall demolition, all drains were plugged and filled with non-shrink concrete. Once the epoxy floors were removed down to the concrete base, R. Baker & Son brought in a BIM scanner system contractor to determine the level of the floors within +/- 1/32” as they needed to be as level as possible, with no high or low points. The BIM contractor identified about a dozen areas that needed to come down in height in order to have a 2-inch total poured concrete floor. Baker crew members prepped and patched several low areas with non-shrink grout to make them level. BIM scans were repeated several times until all high and low points were brought to level. 

The floor was now ready for a new poured resinous surface. Prior to the pour, R. Baker & Son was asked to assist with identifying and filling any open floor areas where conduit and piping had passed through to create a complete seal for the new resinous system. Finally, the entire area was broom swept, cleaned, and vacuumed. The entire floor demolition and preparation project was performed safely to our site-specific safety plan and took approximately three weeks to complete, clearing the way for the next project phase to begin.

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a Minority and Women-Owned Business Enterprise (M/WBE), in business since 1935, is a premier specialized contractor operating in the United States, Canada, and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities of over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

https://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

holding tank agitators, bioprocess facility
Plant Machinery Updates and Replacements

An equipment manufacturer that had worked closely with R. Baker & Son in the past called us regarding a bioprocess facility requiring several key changes to eight large holding tank agitators....
Understanding Physics and Construction are Vital in Demolition
Understanding Physics and Construction are Vital in Demolition

When demolishing a building or other structure, it’s important for the demolition contractor to first understand how it was constructed. The way in which foundations, frames, floors, beams,...
Hazard signs for demolition and construction company R. Baker
Slips, Trips and Falls According to OSHA

According to OSHA, slips, trips, and falls account for the majority of general industry accidents, and they are the greatest hazard in the construction industry. Each year, more than 500,000...
Fire truck being lowered into 9/11 Museum NYC
Spreader Beams a Top Choice for Rigging Stability and Safety

The spreader beam, also known as a spreader bar, is a popular below-the-hook lifting device used to widen lifting points and stabilize and support a load during a crane lift. It consists of a long...
Safety Basics for Demolition Work, photo shows lighting around demolished concrete
Important Safety Basics for Interior Demolition Projects

Demolition can be a dirty business with ever-changing safety concerns. Every project is unique, but there are three basic things that should be addressed in every interior demolition project to help...
Tool and Equipment Tracking - Crane Rigging NYC
Tool and Equipment Tracking - Crane Rigging

Crane rigging requires a lot of tools and equipment. Visitors to a large R. Baker & Son rigging operation might see forklifts, cranes, excavators, generators, articulating booms, front loaders,...
 Sweeping Compounds for Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates
Cleanup of Demolition Dust, Dirt, Silica, and Particulates

Demolition is a dirty job that can produce layers of dirt, dust, and silica that settle on floors and other flat surfaces. There are various techniques and equipment such as misting cannons,...
Rigging equipment, rigging hook, NYC
Auger and Centrifuge Rigging Project

An existing customer called R. Baker & Son needing assistance with rigging equipment duringtheir facility’s annual cleaning and maintenance project. The manufacturing plant was set up for...