All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Baker Works w/ MEP Engineers to Accelerate Plant Relocation

Baker Works w/ MEP Engineers to Accelerate Plant Relocation

Relocating a plant, whether moving across town or across the country, usually means there will be a lapse in production. The longer process is down, the higher the cost, which is why bringing the new plant online as rapidly as possible is imperative to keeping costs in check and preserving your reputation with customers. 

R. Baker & Son completed a manufacturing plant relocation project recently, moving the client’s entire process 400 miles to a neighboring state. The project was rather unique in that the Baker Team worked hand-in-hand with MEP design engineers to fit out the new facility with electrical, plumbing, compressed air, chilled and hot water utilities, sanitary and process waste by going through the entire facility and recording and photographing equipment name plates as well as precise location and layout of equipment. Hundreds of hours were spent planning and coordinating the move with the client to minimize downtime. 

Using the information supplied by R. Baker & Son, the MEP design team ordered an increase in the size of the electrical service and had electrical distribution panels placed throughout the new facility. Sanitary and process drains were cut into the floors and patched at strategic locations. Compressed air headers and chilled water and hot water distribution pipes were run throughout the facility with pinpoint accuracy in anticipation of the new equipment and systems arriving.

The initial estimate for MEP construction was 20 months, but with the unique coordination between R. Baker and the MEP design engineers, a month was shaved off the MEP portion of the plant relocation project. Including long lead times for new electrical substations and transformers, MEP construction took 16 weeks to complete. The move, connection and startup, done in multiple phases, progressed rapidly, taking an additional four weeks to complete. 

R. Baker & Son has completed countless plant relocation projects in our 82-year company history. For more information on plant relocation and other services, please contact us at 732-222-3553 or quote@rbaker.com.

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

holding tank agitators, bioprocess facility
Plant Machinery Updates and Replacements

An equipment manufacturer that had worked closely with R. Baker & Son in the past called us regarding a bioprocess facility requiring several key changes to eight large holding tank agitators....
Understanding Physics and Construction are Vital in Demolition
Understanding Physics and Construction are Vital in Demolition

When demolishing a building or other structure, it’s important for the demolition contractor to first understand how it was constructed. The way in which foundations, frames, floors, beams,...
Hazard signs for demolition and construction company R. Baker
Slips, Trips and Falls According to OSHA

According to OSHA, slips, trips, and falls account for the majority of general industry accidents, and they are the greatest hazard in the construction industry. Each year, more than 500,000...
Fire truck being lowered into 9/11 Museum NYC
Spreader Beams a Top Choice for Rigging Stability and Safety

The spreader beam, also known as a spreader bar, is a popular below-the-hook lifting device used to widen lifting points and stabilize and support a load during a crane lift. It consists of a long...
Safety Basics for Demolition Work, photo shows lighting around demolished concrete
Important Safety Basics for Interior Demolition Projects

Demolition can be a dirty business with ever-changing safety concerns. Every project is unique, but there are three basic things that should be addressed in every interior demolition project to help...
Tool and Equipment Tracking - Crane Rigging NYC
Tool and Equipment Tracking - Crane Rigging

Crane rigging requires a lot of tools and equipment. Visitors to a large R. Baker & Son rigging operation might see forklifts, cranes, excavators, generators, articulating booms, front loaders,...
 Sweeping Compounds for Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates
Cleanup of Demolition Dust, Dirt, Silica, and Particulates

Demolition is a dirty job that can produce layers of dirt, dust, and silica that settle on floors and other flat surfaces. There are various techniques and equipment such as misting cannons,...
Rigging equipment, rigging hook, NYC
Auger and Centrifuge Rigging Project

An existing customer called R. Baker & Son needing assistance with rigging equipment duringtheir facility’s annual cleaning and maintenance project. The manufacturing plant was set up for...