All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Demolition of Uranium Facility, Once the Largest Building in U.S.

Demolition of Uranium Facility, Once the Largest Building in U.S.

When the K-25 uranium enrichment facility was built in the mid-1940s as part of the Manhattan Project in Oak Ridge, Tennessee, it was the world’s largest building under one roof. Seventy years later, demolition of the enormous forty-four acre building was completed after a five-year project.

K-25 was commissioned by the U.S. government during World War II as part of the top-secret race to build the world’s first atomic bomb. Within the walls of the half-mile-long, 2 million square foot U-shaped facility, 12,000 workers produced, via gaseous diffusion, the enriched uranium that was used in atomic bombs dropped on Japan in 1945. Following the war, K-25 remained in operation producing enriched uranium for defense and commercial purposes until it was shut down in 1964. Other buildings at the Oak Ridge facility continued producing uranium until 1987.

Though demolition contractors began taking down the K-25 building in 2008, the complex project was ten years in the making. Due to the hazardous nature of the uranium operation, extensive preparation and remediation were required before demolition could commence. Among numerous Radioactive sludge was removed from a series of underground gunite tanks in 1999, and an onsite waste processing facility was built in 2003 to accept contaminated waste generated during site cleanup. Depleted uranium cylinders were shipped, more than 47,000 tons of metal was removed, several other buildings were demolished, and roads were constructed to accommodate vehicles removing project debris.

Demolition of K-25 was slated to last six years, from 2008 to 2014, but demolition contractors were able to complete the project one year ahead of schedule and approximately $300 million under its original $2.2 billion budget.

R. Baker & Son - All Industrial Services
1 Globe Court
Red Bank, NJ 07701
Phone: 732-222-3553
Web: http://www.rbaker.com

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

 Sweeping Compounds for Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates
Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates

Demolition is a dirty job that can produce layers of dirt, dust, and silica that settle on floors and other flat surfaces. There are various techniques and equipment such as misting cannons,...
Rigging equipment, rigging hook, NYC
Auger and Centrifuge Rigging Project

An existing customer called R. Baker & Son needing assistance with rigging equipment duringtheir facility’s annual cleaning and maintenance project. The manufacturing plant was set up for...
Cooling Tower Dismantling Project
University Cooling Tower Dismantling Project

A large Staten Island mechanical contractor contacted R. Baker & Son to remove a 1,000-ton cooling tower at a university to make way for a new high-efficiency tower and filtration system. The...
Danger sign for rigging, dismantling & demolition site
Rigging, Dismantling & Demolition Project Safety

Safety is the number one priority on every R. Baker & Son project, from dismantling, rigging, and demolition, to plant decommissioning, plant relocation, and environmental services. Safeguards...
construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...
Pre-construction, tablet on table of demolition contractor
Preconstruction Services or Precon

The goal on every construction, renovation or demolition project is to have experienced, reputable contractors bid the project competitively. Preconstruction services, often referred to as precon,...
Asset Recovery: Refurbished Parts and Equipment in High Demand
Asset Recovery: Refurbished Parts and Equipment in High Demand

With supply chain shortages and inflation continuing into 2022, the demand for reconditioned parts and equipment is on the rise. Investment recovery, also known as asset recovery, of aged equipment...
Generator Replacement
Weekend Standby Generator Replacement

A large laboratory and office complex needed to replace an existing standby generator with a new, larger 2000 kW unit with associated automatic transfer switches and day tank. The owner needed the...