All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Selective Demolition and Rigging at Process Plant

Selective Demolition and Rigging at Process Plant

R. Baker & Son recently performed selective demolition and equipment rigging for a process plant construction project. The selective demolition was necessary to prepare the existing facility to receive all of the new mechanical process equipment, including three 5,000 HP boilers with a deaerator, two large compressors, two chillers, boilers with associated economizers, several prefabricated platforms, and two large vertical grinders with elevators and conveyors.

Because the existing access points and doorways were not large enough to accommodate the entry of the equipment, the careful removal of block walls and the installation of steel beams and lintels would be required to allow proper access into the building.

A main challenge during the rigging phase was coordinating bringing the equipment into the building within a tight timeframe according to schedule. Some of the equipment, such as the vertical grinders and conveyors, required assembly in an adjacent outdoor area and had to be brought in vertically due to limited rigging headroom inside the building.

To achieve this, the Baker Team enlarged an existing block opening to 30 ft. wide by 24 ft. high and reinforced it with a pre-engineered support steel beam. The opening was to remain in use as the main loading dock access point. We also created two permanent openings in an interior dividing wall, each measuring 16 ft. wide by 14 ft. high, that would be utilized for forklift traffic and to facilitate the movement of materials throughout the facility. The openings were finished with concrete and prime-painted for future finishing use.

An 80-ton crane with an extended jib, two articulating boom lifts, and a large Lull were used to lift and move the mechanical and process equipment through the opening and into the building. All the equipment was moved in safely and set in place within the allotted timeframe to the client’s full satisfaction.

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Several large steam-to-hot-water heat exchangers
Quick Mobilization for Pilot Plant Dismantling and Demolition

When a building consolidation commitment required our client to dismantle and demolish a 30,000 square-foot pilot plant immediately, they turned to R. Baker & Son. Having rigged much of the...
Rigging, completely assembling, and setting 12 large fiberglass cylindrical tanks, each with a 17,000-gallon capacity.
Rising to a Rigging Challenge: Custom Tank Installation in North Philadelphia

The Project Scope As part of a major rigging project in North Philadelphia, R. Baker & Son faced a complex installation challenge: rigging, completely assembling, and setting 12 large...
Nine downflow booths carefully dismantled and packaged for refurbishment during pharmaceutical lab renovation.
Negative Pressure Demolition in an Active Pharmaceutical R&D Laboratory

R. Baker & Son had the unique opportunity to return to a pharmaceutical R&D laboratory project we had successfully completed years earlier, where our riggers and millwrights originally...
Industrial building demolition with advanced machinery by R. Baker & Son
R. Baker & Son: Experts in Modern Demolition Technology

Building demolition technology has undergone remarkable transformations over the decades, reflecting advancements in engineering, safety standards, and environmental stewardship. The evolution from...
Ground Penetrating Radar (GPR) - Demolition Contractor R. Baker & Son
Ground Penetrating Radar - Must have tool in Concrete Cutting and Demolition

At R Baker we have been involved with many demolition projects each one having its own set of challenges. When cutting concrete in an active facility or performing select or partial demolition you...
R. Baker & Son riggers installing 24 pharmaceutical bioreactors with platforms and safety railings in upstate New York facility
How We Installed 24 Bioreactors in Just 4 Weeks (NY Pharma)

R. Baker & Son recently completed a complex pharmaceutical equipment installation project after receiving a referral from a senior process engineer at a leading New Jersey design firm. The...
Professional Rigging Services: Expert Equipment Handling and Installation to Avoid Costly Damage
Professional Rigging: Why Equipment Installation Requires Expert Expertise

Comprehensive Rigging Services Across Industries R Baker & Son's rigging teams collaborate with equipment manufacturers across virtually every major industry. This extensive experience...
Professional building demolition with hydraulic shear in urban setting
Professional Building Demolition: Why Structural Knowledge Matters

To be successful in professional building demolition and dismantling, you need to be an experienced demolition expert in taking buildings down - whether in whole, in part, or in pieces. Providing...