All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|            
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Demolition: A Little Ingenuity Goes a Long Way

Demolition of a Utility Tunnel

Over decades at a Central New Jersey facility, a long MEP utility tunnel was used to carry various plumbing, HVAC, electrical and control lines. When systems began to age and several plumbing lines began to show signs of deterioration and leaking recently, plans were developed to replace the old pipes with new. It was discovered during this planning process that there were many old, abandoned electrical and HVAC piping lines that required removal. The project became a cleanup of the tunnel system aimed not only at replacing what was failing, but a demolition operation to remove what was no longer in use so that future lines could be installed. 

The utility tunnel functioned as the backbone of the facility, running below multiple buildings servicing various areas, with the tunnel ceiling and walls supporting a multitude of piping and conduit. Demolition company & rigging services R. Baker & Son was brought in to meet the unique challenge of coming up with a way to safely and efficiently remove demolition waste from the tunnel and bring new materials. Though the tunnel had multiple entrances and exits, it was important that the demolition waste be routed to the end of the tunnel nearest the loading dock for removal. To achieve this, the Baker Team built a custom heavy-duty trolley, six feet long by three feet wide, with rubber wheels and 3-foot high posts to contain pipe and conduit, as well as rubber wheels on the sides to roll along the tunnel’s walls to eliminate friction. It was operated using steel cables, pulleys and an electric winch. A few test runs with 400 lbs. of weight were successful. The trolley proved so successful in the demolition of the tunnel and transport of new materials that the customer purchased it at the end of the project, parking it in the tunnel for future needs. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
http://www.rbaker.com
732-222-3553

Full News Archive

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

University Hospital NY - Renovation Project
Hospital Renovation Project

A large university hospital in New York had several buildings on campus. The central building, a 75,000 sq. ft. four-story structure with a mechanical penthouse was the first to be erected in 1944,...
Demolition Contractor: Earning & Keeping Our Reputation
Demolition Contractor: Earning and Keeping Our Great Reputation

A demolition contractor’s reputation is everything, and what can take decades to build can be lost very quickly if great care is not taken. Customers have specific overall expectations, most...
Rigging Setting the Final Pieces of Process Equipment
Rigging Setting the Final Pieces of Process Equipment

A large, ongoing pharmaceutical project was facing a dilemma. With most work progressing smoothly and on-schedule, equipment for one very important process area would not be arriving onsite until the...
Demolition Project Goes Underground
Demolition Project Goes Underground

A 175,000 square-foot OTC R&D and production building, constructed in the early 1960s, was undergoing complete interior demolition to be repurposed as a pilot facility. The demolition schedule...
Copper Recycling Offsets Dismantling Project Costs
Copper Recycling Offsets Dismantling Project Costs

A large electrical-mechanical contractor hired R. Baker & Son to perform all of the electrical equipment dismantling and mechanical equipment removal at an old vitamin production facility...
CUP Multi-Phase Selective Demolition Project: Demo by Color
CUP Multi-Phase Selective Demolition Project: Demo by Color

An aging central utility plant serving a large northern New Jersey hospital was due for complete renovation, including the replacement of almost all equipment including boilers, chillers, cooling...
Rigging Safety Guidelines - Industrial Services
Rigging Safety Guidelines

Safety is paramount at R. Baker & Son, which is why we strictly observe all rigging safety regulations, guidelines and procedures on every lift we do. Guidelines for rigging safety: Inspect...
R. Baker Salvages Fixtures for Reuse on Plant Consolidation Project
R. Baker Salvages Fixtures for Reuse on Plant Consolidation

A longtime client approached R. Baker & Son with a plant relocation project in which operations at several partially-occupied buildings were to be moved to a single 200,000 sq. ft. building...