All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Weekend Standby Generator Replacement

Generator Replacement

A large laboratory and office complex needed to replace an existing standby generator with a new, larger 2000 kW unit with associated automatic transfer switches and day tank. The owner needed the project to be completed over a long weekend beginning on Friday morning and ending on Monday afternoon, so the electrical contractor tasked with replacing the generator chose R. Baker & Son to assist in this critical replacement project. 

The electrical contractor had prepared for the weekend installation over a few months. Due to the critical nature of the project, a site-specific safety plan was developed along with a method of procedure specifying which teams would be performing certain tasks, and when. The weather forecast looked good, with cool temperatures and a few scattered showers expected over the weekend. 

R. Baker & Son and the electrical crew arrived early on Friday morning. While electricians were shutting down and disconnecting electrical power from the generator, R. Baker millwrights and rigging team members were simultaneously disassembling the old standby generator and separating the diesel engine from the condenser/fan section. A second rigging team removed the four large louvers and dampers, allowing access to a rear parking lot area. By late afternoon on Friday, the project had progressed to where the 80-ton hydraulic crane could begin removing pieces of the generator. 

On Saturday, the Baker rigging team had removed the remains of the old generator by mid-morning and the area was cleaned and prepped with pre-fabricated steel pieces. Riggers carefully brought in the new generator using spreader bars, slings, chain blocks, and a fork lift and precisely set it in place where new electrical conduit and fuel lines sat ready for connection. The Baker Team assisted the electrical contractor with installing ATS switches, mounting the day tank, installing the exhaust system, and various other tasks. The outside louvers and dampers were reinstalled, and all remaining debris was removed. Because of all the intensive preparation, pre-fabrication, and close coordination between the electrical and rigging teams, the new generator was wired and ready for startup and testing bright and early on Tuesday morning. 

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a Minority and Women-Owned Business Enterprise (M/WBE), in business since 1935, is a premier specialized contractor operating in the United States, Canada, and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities of over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

https://rbaker.com/rigging-contractors.php

Full News Archive

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Rigging and Replacing Old Equipment - Boilers, Chilling Towers
R. Baker Seamlessly Rigging and Replacing Old Equipment

Recently, a large hospital in central New Jersey successfully completed extensive HVAC and electrical changes. These changes, which were a significant undertaking, included replacing two chillers and...
Hospital Corridor Before Demolition by R. Baker & Son
R. Baker & Son Hospital Wing Interior Demolition

R. Baker & Son was awarded a project to perform interior demolition of a 55,000 sq/ft three-story patient area in a New York hospital. The wing, erected in the early 1980s and renovated in the...
Rigging Equipment Contractor - Rigging lift in NYC
R. Baker & Son's Rigging Expertise Shines in Pharma Expansion

R. Baker & Son, an industrial tri-state contractor specializing in selective demolition and rigging services, showcased our exceptional skills during a challenging project at a high-tech...
demolition equipment at JFK NYC
R. Baker & Son Comprehensive Equipment Management Strategy

Demolition projects demand specialized equipment, machines, and tools to ensure safe and efficient execution. At R. Baker & Son, we employ an array of assets, including excavators, cranes,...
rigging project planning, man welding steel beams
Expert Rigging: Meticulous Planning for Safe Lift Projects

A major rigging project demands meticulous planning and execution. While the actual lift may only span a day or two, it represents the culmination of weeks or even months of intense...
Rigging Equipment, skyline NYC, Women Owned Business
Efficient Rigging and Equipment Setup: Planning and Collaboration

R. Baker & Son was contacted by a large mechanical contractor with whom we have worked in the past and who works in the New Jersey-Philadelphia area. They had a large renovation project that...
Environmental Solutions for Dismantling, Decommissioning and Demolition
Eco-Friendly Solutions for Dismantling, Demo & Decommissioning

Demolition, dismantling, or decommissioning of industrial facilities is a complex process that requires meticulous planning and execution. These sites often contain hazardous chemicals, substances,...
Selective Demolition and Rigging at Process Plant
Selective Demolition and Rigging at Process Plant

R. Baker & Son recently performed selective demolition and equipment rigging for a process plant construction project. The selective demolition was necessary to prepare the existing facility to...