All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Tricky Job With A Very Aggressive Schedule

Tricky Job With A Very Aggressive Schedule

R. Baker & Son was contracted by a pharmaceuticals firm to perform selective demolition in their central utility plant.  The company was slated to bring an innovative new drug to market, and it was especially critical that research and development went undisrupted.

The central utility plant supported many of the facility’s operations with compressed air, chilled water, steam, nitrogen and DI water. The project required much of the old equipment to be removed and replaced by new equipment.  This necessitated that crew members remove old housekeeping pads with jackhammers and saw-cut new drains into concrete.  With adjacent R&D laboratories lining two walls of the CUP and a vivarium not far away, R. Baker & Son developed a detailed schedule in coordination with facility owners to suppress dust and minimize noise, and vibration.

Selective demolition and dismantling took place as a precise, step-by-step process. System piping and other equipment were carefully traced, identified, and marked for appropriate disposition. Hazardous substances and materials, including refrigerants and lead paint, were carefully removed and abated, and proper lockout / tagout procedures were followed.   
To complicate the already-challenging project, the pharmaceuticals firm moved the completion date up by three months due to increased urgency in bringing the new product to market.  The project kicked into an even higher gear and shifts were added in order to complete the project on time.

R. Baker & Son developed a detailed Rigging and Routing plan when it came time to move new equipment into the facility.  After double-verifying weights and dimensions, team members determined how and when to move the equipment, and through which access points.  Many pieces of equipment required careful disassembly in order to maneuver it into the building. In some instances, new equipment was installed in the midst of demolition.

As new equipment was rigged, installed, and readied to be brought online alongside existing equipment, crews went over a detailed checklist to ensure a smooth transition from old equipment to new.  This was done without system interruption whenever possible, but when unavoidable, the work generally took place when the facility was unoccupied and details were meticulously planned and scheduled with owners.

Once the new systems were up and running, Baker crews concentrated on cleanup and punch list items.  When all was said and done, the new central utility plant equipment was seamlessly integrated, and the project was successfully completed on time.  Crews were treated to catered lunch on site were pleased. 

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services is the premier specialized contractor in the United States, Canada and Puerto Rico.  The Service-Disabled Veteran-Owned Small Businesses (SDVOSB) has been in business since 1935, has over 100 employees, an exemplary safety record (We have been directly involved in four (4) sites that received VPP OSHA Safety Awards) and is financially strong (bonding capabilities over $10 Million).  Capabilities include industrial and commercial demolition, rigging, machinery & plant moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, wrecking, selective demolition , demolition contractors in NJ and warehousing.

R. Baker & Son All Industrial Services
1 Globe Street
Red Bank, NJ 07701
Phone: 732-222-3553
Fax: 732-450-0311

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Fire truck being lowered into 9/11 Museum NYC
Spreader Beams a Top Choice for Rigging Stability and Safety

The spreader beam, also known as a spreader bar, is a popular below-the-hook lifting device used to widen lifting points and stabilize and support a load during a crane lift. It consists of a long...
Safety Basics for Demolition Work, photo shows lighting around demolished concrete
Important Safety Basics for Interior Demolition Projects

Demolition can be a dirty business with ever-changing safety concerns. Every project is unique, but there are three basic things that should be addressed in every interior demolition project to help...
Tool and Equipment Tracking - Crane Rigging NYC
Tool and Equipment Tracking - Crane Rigging

Crane rigging requires a lot of tools and equipment. Visitors to a large R. Baker & Son rigging operation might see forklifts, cranes, excavators, generators, articulating booms, front loaders,...
 Sweeping Compounds for Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates
Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates

Demolition is a dirty job that can produce layers of dirt, dust, and silica that settle on floors and other flat surfaces. There are various techniques and equipment such as misting cannons,...
Rigging equipment, rigging hook, NYC
Auger and Centrifuge Rigging Project

An existing customer called R. Baker & Son needing assistance with rigging equipment duringtheir facility’s annual cleaning and maintenance project. The manufacturing plant was set up for...
Cooling Tower Dismantling Project
University Cooling Tower Dismantling Project

A large Staten Island mechanical contractor contacted R. Baker & Son to remove a 1,000-ton cooling tower at a university to make way for a new high-efficiency tower and filtration system. The...
Danger sign for rigging, dismantling & demolition site
Rigging, Dismantling & Demolition Project Safety

Safety is the number one priority on every R. Baker & Son project, from dismantling, rigging, and demolition, to plant decommissioning, plant relocation, and environmental services. Safeguards...
construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...