All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Remote-controlled Brokk demolition machine performing precise concrete breaking on a high-risk construction job site.
How Remote Controlled Machinery Improves Demolition & Job Site Safety

According to OSHA, falls remain the number one safety issue on construction job sites. Struck-by incidents, electrocution, and caught-in or caught-between hazards round out what OSHA calls the Focus...
R. Baker & Son riggers setting water-cooled centrifugal chillers for data center cooling availability.
Data Center Rigging & MEP Installation: Keeping Projects on Schedule

Safe, efficient rigging and assembly of data center MEP systems starts with understanding how a data center operates. That means knowing what mechanical and electrical equipment is required, how each...
An 80-ton crane hoisting a new MRI machine during a medical equipment replacement project
Swapping an 8-Ton MRI in 48 Hours: Inside a Complex Medical Rigging Project

Six months after rigging two MRI machines, a CT scanner, a PET scanner, and their associated chillers and cooling equipment into a brand-new medical treatment facility, we got another call from the...
Precision Chiller Dismantling & Mechanical Retrofit Case Study
Precision Chiller Dismantling & Mechanical Retrofit Case Study

A local New Jersey representative for a major chiller manufacturer recommended R. Baker & Son for a demanding chiller change-out project. The scope: remove two 1,200-ton chillers and their...
Discover how a custom negative pressure wall and real-time monitoring protected a pharmaceutical cleanroom during high-stakes facility demolition.
How to Protect Active Cleanrooms During Demolition: A Negative Pressure Wall Case Study

Protecting a client's environment during demolition and renovation work has always been part of what we do at R. Baker & Son. Anyone in the industry knows ICRA protection, the barrier system...
rigging medical equipment into a hospital - R. Baker & Son
Just-in-Time Rigging Keeps a Hospital Running During a Critical Enabling Project

R. Baker & Son received a call from a concerned South Jersey mechanical contractor facing a complex rigging project on a tight deadline. Another rigging contractor had passed on the job late in...
Riggers assembling tower crane sections during construction - R. Baker & Son - Master Riggers.
How Mobile and Tower Cranes Are Assembled & Dismantled

Mobile cranes come in many styles, shapes, and sizes, with the hydraulic crane and the luffing jib being the most common. R. Baker & Son has worked with just about every mobile crane on the...
Demolition concrete debris fed into an industrial crusher for recycling
7 Ways Demolition Protects Communities & the Planet

7 Ways Demolition Builds Better Communities -And Why It Matters When most people picture demolition, they see dust clouds and falling walls. What they don't see is the careful planning,...