R. Baker & Son Dismantles Cooling Towers at Active Facility

R. Baker & Son All Industrial Services, a specialized dismantling, rigging and demolition contractor, completed the total dismantlement of two cooling towers at an active pharmaceutical plant in New Jersey. The work was part of a larger cooling tower replacement and upgrade project by Skanska USA Building.

The basic scope of work consisted of the total dismantlement of two wooden cooling towers that were approximately 60 feet high.  Each tower needed to be carefully dismantled, along with associated piping, stairs, hangers and supports, down to top of concrete dike slab. It was critical that the concrete slab of the dike not be damaged as this was going to be re-utilized for new construction.  The work also needed to be conducted with the utmost attention to safety for workers and the surrounding facility workers and nearby structures.  Active lines and structures were on all sides of the work area and also in close proximity to an active plant road with pedestrian and vehicular traffic.
Prior to any dismantling work being conducted, several important pre-dismantlement tasks needed to be completed.  All utilities and active lines to the cooling towers were isolated and made safe.  Asbestos containing materials were properly removed and abated.   As safety was paramount, chain link fencing with green screen mesh was placed around the work area.  In addition, debris netting was placed in strategic locations to ensure no debris landed outside the work zone.

Following these tasks, safety procedures and safety plans were implemented to ensure a safe dismantling project. Damon Kozul, PE, CHMM, Corp. Safety Officer, worked closely with Carl Finkelson, Project Manager, to ensure that safety was first and foremost on the project. A safety video was watched by all employees and each worker was instructed on the proper PPE required for the project.  Beyond the basic Level D PPE, high visibility safety vests were worn by all workers.  In addition, a JSA (Job Safety analysis) was developed and implemented for each day of work.

Dismantling of the two cooling towers started with the salvage of the fans for re-use and spare parts.  In order to rig this equipment safely, a Grove hydraulic 100-ton capacity all terrain crane was utilized.  R. Baker & Son assigned several of their key rigging experts, including T.J. Indelweiss and Mario Laka, to this phase of the project to ensure the task was completely safely and on schedule.  Under the management of Mr. Finkelson, the fan units were carefully extracted from the cooling tower units, rigged down without any damaged and then placed in the client’s storage area.

Following the equipment salvage, the interior of the dike for the cooling towers was cleaned of piping and all diffusers.  This selective demolition was done prior to any structural demo to make it easier to keep materials segregated for clean up and recycling.

Due to the proximity to active lines and structures, mechanical demolition using excavators could not be performed.  In order to safely take down the cooling towers, R. Baker & Son developed a methodology to utilize skilled dismantlers in manlifts with hand tools.  A 60 and 80 foot Genie manlift was lifted into the diked area using the 100-ton capacity crane.  The manlifts were then utilized by dismantlers with saws and other hand tools to methodically dismantle the wooden towers section by section.  As a section was demolished, debris was immediately removed using Bobcat S150 and S185 skid steers with demolition buckets.  This process continued until the concrete and steel base of the units was reached.

To demolish the concrete and steel beam bases, R. Baker & Son once again utilized the Grove 100-ton capacity crane to carefully lift equipment into the diked area.  Two (2) Bobcat 341 mini excavators with concrete breakers and buckets were utilized for this phase.  These machines easily demolished the cooling tower bases into rubble while not damaging the slab below which was to be utilized for the new construction.  The demolished concrete was loaded out of the diked area for offsite recycling.

The client had set a very demanding schedule that necessitated R. Baker & Son to work weekends.  Due to R. Baker & Son’s attention to pre-planning, safety implementation and the skilled workmanship by Mr. Finkelson’s crew, the project was safely completed on schedule.

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services is the premier specialized contractor for dismantlement, decommissioning and demolition in the United States, Canada and Puerto Rico.  The veteran owned company has been in business since 1935, has over 100 employees, an exemplary safety record (We have been directly involved in four (4) sites that received VPP OSHA Safety Awards) and is financially strong (bonding capabilities over $10 Million).  Capabilities include total plant and facility dismantlement, decommissioning, demolition, plant relocations and re-installations as well as heavy equipment rigging and machinery moving, millwright services and onsite concrete crushing.

Corporate Contact Information

R. Baker & Son All Industrial Services
1 Globe Street
Red Bank, NJ 07701
Phone: 732-222-3553
Fax: 732-450-0311
Website: www.rbaker.com

For more information visit our website or contact Damon Kozul, PE, CHMM at dkozul@rbaker.com

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Fire truck being lowered into 9/11 Museum NYC
Spreader Beams a Top Choice for Rigging Stability and Safety

The spreader beam, also known as a spreader bar, is a popular below-the-hook lifting device used to widen lifting points and stabilize and support a load during a crane lift. It consists of a long...
Safety Basics for Demolition Work, photo shows lighting around demolished concrete
Important Safety Basics for Interior Demolition Projects

Demolition can be a dirty business with ever-changing safety concerns. Every project is unique, but there are three basic things that should be addressed in every interior demolition project to help...
Tool and Equipment Tracking - Crane Rigging NYC
Tool and Equipment Tracking - Crane Rigging

Crane rigging requires a lot of tools and equipment. Visitors to a large R. Baker & Son rigging operation might see forklifts, cranes, excavators, generators, articulating booms, front loaders,...
 Sweeping Compounds for Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates
Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates

Demolition is a dirty job that can produce layers of dirt, dust, and silica that settle on floors and other flat surfaces. There are various techniques and equipment such as misting cannons,...
Rigging equipment, rigging hook, NYC
Auger and Centrifuge Rigging Project

An existing customer called R. Baker & Son needing assistance with rigging equipment duringtheir facility’s annual cleaning and maintenance project. The manufacturing plant was set up for...
Cooling Tower Dismantling Project
University Cooling Tower Dismantling Project

A large Staten Island mechanical contractor contacted R. Baker & Son to remove a 1,000-ton cooling tower at a university to make way for a new high-efficiency tower and filtration system. The...
Danger sign for rigging, dismantling & demolition site
Rigging, Dismantling & Demolition Project Safety

Safety is the number one priority on every R. Baker & Son project, from dismantling, rigging, and demolition, to plant decommissioning, plant relocation, and environmental services. Safeguards...
construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...