All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Substantial Cost Savings in Space Repurposing Project

Demolition contractor doing environmental cleanup

R. Baker & Son was contracted by a long time customer with an order to perform demolition, dismantling and equipment relocation work at an old production facility that was to be repurposed. Production rooms and corridors occupied the ground floor of the two-story building and a mechanical and electrical penthouse were on the second floor.

With safety as our first priority, Phase One of the project required the dismantling and removal of all air handlers, exhaust fans, heat exchangers, pumps, piping and motor control centers. Next, Baker removed concrete housekeeping pads and miscellaneous steel throughout the building. All MEP equipment was removed using two heavy duty Lull 1044Cs and a JLG 5394RT and moved to rigging and staging areas for further dismantling, separation of materials, and recycling.  The facility’s maintenance department worked closely with the Baker team to identify and salvage existing pumps and parts for reuse in other buildings or for attic stock. 

Phase Two of the project required an 80-ton crane to safely remove roof exhaust fans, condensers, package AHUs, piping and ductwork. The third phase entailed the removal of several large pieces of process equipment and other machinery that was separated and match marked for use at another facility, including two lyophilizers, a large fluid bed and granulator, several isolators and glove boxes, as well as large in-floor scales and several 5,000 gallon process tanks.  Walls and ceilings were successfully removed while identifying and preserving recently-installed fiber optic inner ducts during demolition and dismantling. Floor demolition was more challenging and time consuming, requiring removal of thick, sloped epoxy floors with pneumatic hammers and scrapers. Facility restrooms, still in good shape, were left intact as a value engineering cost-savings item. 

Exterior blockwork was thoroughly cleaned, pointed and power washed using several articulating booms. As a cost saving measure, windows were cleaned and re-caulked for reuse. Where required, floors on both levels were flash-patched. R. Baker & Son had zero safety incidents on the project while adhering to an aggressive schedule and providing $260,000 in cost savings. 

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a  Service-Disabled Veteran-Owned Business (SDVOB)  in business since 1935, is a premier specialized contractor operating in the United States, Canada and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553
http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

holding tank agitators, bioprocess facility
Plant Machinery Updates and Replacements

An equipment manufacturer that had worked closely with R. Baker & Son in the past called us regarding a bioprocess facility requiring several key changes to eight large holding tank agitators....
Understanding Physics and Construction are Vital in Demolition
Understanding Physics and Construction are Vital in Demolition

When demolishing a building or other structure, it’s important for the demolition contractor to first understand how it was constructed. The way in which foundations, frames, floors, beams,...
Hazard signs for demolition and construction company R. Baker
Slips, Trips and Falls According to OSHA

According to OSHA, slips, trips, and falls account for the majority of general industry accidents, and they are the greatest hazard in the construction industry. Each year, more than 500,000...
Fire truck being lowered into 9/11 Museum NYC
Spreader Beams a Top Choice for Rigging Stability and Safety

The spreader beam, also known as a spreader bar, is a popular below-the-hook lifting device used to widen lifting points and stabilize and support a load during a crane lift. It consists of a long...
Safety Basics for Demolition Work, photo shows lighting around demolished concrete
Important Safety Basics for Interior Demolition Projects

Demolition can be a dirty business with ever-changing safety concerns. Every project is unique, but there are three basic things that should be addressed in every interior demolition project to help...
Tool and Equipment Tracking - Crane Rigging NYC
Tool and Equipment Tracking - Crane Rigging

Crane rigging requires a lot of tools and equipment. Visitors to a large R. Baker & Son rigging operation might see forklifts, cranes, excavators, generators, articulating booms, front loaders,...
 Sweeping Compounds for Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates
Cleanup of Demolition Dust, Dirt, Silica, and Particulates

Demolition is a dirty job that can produce layers of dirt, dust, and silica that settle on floors and other flat surfaces. There are various techniques and equipment such as misting cannons,...
Rigging equipment, rigging hook, NYC
Auger and Centrifuge Rigging Project

An existing customer called R. Baker & Son needing assistance with rigging equipment duringtheir facility’s annual cleaning and maintenance project. The manufacturing plant was set up for...