All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Substantial Cost Savings in Space Repurposing Project

Demolition contractor doing environmental cleanup

R. Baker & Son was contracted by a long time customer with an order to perform demolition, dismantling and equipment relocation work at an old production facility that was to be repurposed. Production rooms and corridors occupied the ground floor of the two-story building and a mechanical and electrical penthouse were on the second floor.

With safety as our first priority, Phase One of the project required the dismantling and removal of all air handlers, exhaust fans, heat exchangers, pumps, piping and motor control centers. Next, Baker removed concrete housekeeping pads and miscellaneous steel throughout the building. All MEP equipment was removed using two heavy duty Lull 1044Cs and a JLG 5394RT and moved to rigging and staging areas for further dismantling, separation of materials, and recycling.  The facility’s maintenance department worked closely with the Baker team to identify and salvage existing pumps and parts for reuse in other buildings or for attic stock. 

Phase Two of the project required an 80-ton crane to safely remove roof exhaust fans, condensers, package AHUs, piping and ductwork. The third phase entailed the removal of several large pieces of process equipment and other machinery that was separated and match marked for use at another facility, including two lyophilizers, a large fluid bed and granulator, several isolators and glove boxes, as well as large in-floor scales and several 5,000 gallon process tanks.  Walls and ceilings were successfully removed while identifying and preserving recently-installed fiber optic inner ducts during demolition and dismantling. Floor demolition was more challenging and time consuming, requiring removal of thick, sloped epoxy floors with pneumatic hammers and scrapers. Facility restrooms, still in good shape, were left intact as a value engineering cost-savings item. 

Exterior blockwork was thoroughly cleaned, pointed and power washed using several articulating booms. As a cost saving measure, windows were cleaned and re-caulked for reuse. Where required, floors on both levels were flash-patched. R. Baker & Son had zero safety incidents on the project while adhering to an aggressive schedule and providing $260,000 in cost savings. 

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a  Service-Disabled Veteran-Owned Business (SDVOB)  in business since 1935, is a premier specialized contractor operating in the United States, Canada and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553
http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Safety is a Mindset at R. Baker & Son 
Safety is a Mindset at R. Baker & Son

Every construction project is different, from site to site, in size and scope, and in the overall approach to safe work practices. Where many projects take safety very seriously, plenty of others are...
Water Treatment Systems
Disassemble and Relocate Water Treatment Systems

When a food manufacturerand longtime R. Baker & Son clientdecided to sell off their existing reverse osmosis and pH waste neutralization systems at their northeastern Pennsylvania manufacturing...
Dust, Noise, and Vibration on Demolition Sites
Planning for Dust, Noise, and Vibration on Demo Projects

Planning for dust, noise, and vibration can be an important part of demolition and dismantling, particularly in and near occupied buildings and in densely-populated areas. R. Baker & Son works...
Machinery moving, assembly project, used conveyor system
Machinery Moving and Assembly Project

A manufacturer was referred to R. Baker & Son for help with a plant expansion project. A used conveyor system was being added to their production line connecting several newly-leased pieces of...
Rigging and Assembling Test Equipment-NJ Processing Facility
Rigging and Assembling Test Equipment-NJ Processing Facility

An R. Baker & Son previous client was rapidly growing and had plans to refine and expand their operation. Their R&D test team had been working with several engineering firms to design and...
Concrete Slab X-Rays Enable Accurate Cutting and Drilling
Concrete Slab X-Rays Enable Accurate Cutting and Drilling

R. Baker & Son was recently involved in a selective demolition project at a four-story, 90,000 sq. ft. R&D lab facility with basement and penthouse where all forty-six laboratories would be...
Baker Wins 3 Highwire Platinum Safety Awards
R. Baker & Son Wins 3 Highwire 2022 Platinum Safety Awards

R. Baker & Son - All Industrial Services was awarded 3 HighwirePlatinum Safety Awards for 2022! The Safety Assessment Program reviews a company’s historic safety performance and current...
Rigging and Assembly in New Storage and Maintenance Facility
Rigging and Assembly in New Storage and Maintenance Facility

A longtime customer referred R. Baker & Son to a company in need of immediate assistance at their company’s new storage facility. Truckloads of various materials and equipment were arriving...