What is a Critical Lift?

Image of Critical Lifting

In the crane and rigging industry, a critical lift is a rigging activity in which a comprehensive plan is necessary to minimize risk of crane failure or catastrophic loss. As for the term “critical lift”, though there is no universally-accepted single definition or industry standard used for categorization, there are a number of items that are common to various agencies and rigging industry associations. OSHA characterizes the definition thusly: a critical lift is one that a) exceeds 75% of the rated capacity of the crane or derrick, or b) requires the use of more than one crane or derrick. Various other government agencies and industry associations such as NIOSH, the US Army Corps of Engineers, and the Department of Energy use their own criteria to classify a critical lift that will require development of a critical lift plan.  Following are some of the most commonly-appearing elements of a critical lift (keeping in mind that specific projects have unique conditions that should be taken into consideration): 

  • Any lift that requires more than one crane 

  • Loads exceeding 75% of a crane’s rated capacity

  • Lifting of personnel

  • Load suspension above rigging personnel

  • Loads not in view of the crane operator

  • Loads of exceptional value

  • Loads that have the potential for becoming unstable during rigging

If it is determined that a lift is to be considered critical, a detailed critical lift plan must be prepared. Following an analysis by qualified rigging personnel, a critical lift plan should include details such as size and weight of the load, equipment needed, boom length and angle, crane and boom positioning, required personnel, crane capacity, sequencing, and environmental conditions, among others.  The critical lift plan should be thoroughly reviewed with the rigging crew prior to the lift to ensure that all necessary details and required safety procedures are in place. 

R. Baker & Son, a leading rigging contractor since 1936, has conducted countless critical lifts for a vast array of clients in a variety of industries throughout the U.S., Canada and Puerto Rico. We are staffed by experienced master riggers, engineers, and skilled rigging tradespersons and equipped with all of the necessary equipment to handle even the most complex rigging projects with the highest safety standards. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553
http://www.rbaker.com

Full News Archive

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

 Sweeping Compounds for Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates
Cleanup of Demolition Dust, Dirt, Silica, and Other Particulates

Demolition is a dirty job that can produce layers of dirt, dust, and silica that settle on floors and other flat surfaces. There are various techniques and equipment such as misting cannons,...
Rigging equipment, rigging hook, NYC
Auger and Centrifuge Rigging Project

An existing customer called R. Baker & Son needing assistance with rigging equipment duringtheir facility’s annual cleaning and maintenance project. The manufacturing plant was set up for...
Cooling Tower Dismantling Project
University Cooling Tower Dismantling Project

A large Staten Island mechanical contractor contacted R. Baker & Son to remove a 1,000-ton cooling tower at a university to make way for a new high-efficiency tower and filtration system. The...
Danger sign for rigging, dismantling & demolition site
Rigging, Dismantling & Demolition Project Safety

Safety is the number one priority on every R. Baker & Son project, from dismantling, rigging, and demolition, to plant decommissioning, plant relocation, and environmental services. Safeguards...
construction worker performing a multi heat exchanger changeout 
Baker Performs Multi Heat Exchanger Changeout

Back in early 2021, R. Baker & Son took part in a food manufacturing construction project in which we performed rigging and assembly of six large, high-pressure steam ovens over a ten-week...
Pre-construction, tablet on table of demolition contractor
Preconstruction Services or Precon

The goal on every construction, renovation or demolition project is to have experienced, reputable contractors bid the project competitively. Preconstruction services, often referred to as precon,...
Asset Recovery: Refurbished Parts and Equipment in High Demand
Asset Recovery: Refurbished Parts and Equipment in High Demand

With supply chain shortages and inflation continuing into 2022, the demand for reconditioned parts and equipment is on the rise. Investment recovery, also known as asset recovery, of aged equipment...
Generator Replacement
Weekend Standby Generator Replacement

A large laboratory and office complex needed to replace an existing standby generator with a new, larger 2000 kW unit with associated automatic transfer switches and day tank. The owner needed the...