The Complexities of Plant Relocation

The Complexities of Plant Relocation

Plant relocation can be a complex undertaking that requires meticulous planning, communication, and preparation. A comprehensive schedule must be developed that will seamlessly ramp down the vacating facility while simultaneously phasing in production at the new plant. This should include testing and commissioning. Close coordination and communication among the plant relocation contractor, designers, and facility managers is vital to accurate schedule development. 

Detailed drawings of the equipment layout in the vacating plant will be needed when planning utilities and locating equipment in the new facility.  Existing equipment must be assessed to determine which will be relocated reused, and whether it will require refurbishment. Equipment slated for plant relocation must meets local code in the new facility. 

All relocated equipment must be meticulously identified, logged, and tagged, and utility connections and separation points must be accurately noted. Utility systems and structural modifications needed in the new plant must be identified, designed and installed to ensure that equipment installation, testing, and commissioning can smoothly occur without a hitch. 

R. Baker & Son provides comprehensive turnkey service for all phases of industrial and commercial plant relocation.  Services include dismantlement and relocation planning, match marking, heavy machinery moving, rigging, relocation, reassembly, reinstallation, and startup. Projects are performed with minimal disruption regardless of scale. 

R. Baker & Son All Industrial Services
1 Globe Court
Red Bank, NJ 07701
Phone: 732-222-3553
Fax: 732-450-0311
Follow Us On Facebook

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Precision Chiller Dismantling & Mechanical Retrofit Case Study
Precision Chiller Dismantling & Mechanical Retrofit Case Study

A local New Jersey representative for a major chiller manufacturer recommended R. Baker & Son for a demanding chiller change-out project. The scope: remove two 1,200-ton chillers and their...
Discover how a custom negative pressure wall and real-time monitoring protected a pharmaceutical cleanroom during high-stakes facility demolition.
How to Protect Active Cleanrooms During Demolition: A Negative Pressure Wall Case Study

Protecting a client's environment during demolition and renovation work has always been part of what we do at R. Baker & Son. Anyone in the industry knows ICRA protection, the barrier system...
rigging medical equipment into a hospital - R. Baker & Son
Just-in-Time Rigging Keeps a Hospital Running During a Critical Enabling Project

R. Baker & Son received a call from a concerned South Jersey mechanical contractor facing a complex rigging project on a tight deadline. Another rigging contractor had passed on the job late in...
Riggers assembling tower crane sections during construction - R. Baker & Son - Master Riggers.
How Mobile and Tower Cranes Are Assembled & Dismantled

Mobile cranes come in many styles, shapes, and sizes, with the hydraulic crane and the luffing jib being the most common. R. Baker & Son has worked with just about every mobile crane on the...
Demolition concrete debris fed into an industrial crusher for recycling
7 Ways Demolition Protects Communities & the Planet

7 Ways Demolition Builds Better Communities -And Why It Matters When most people picture demolition, they see dust clouds and falling walls. What they don't see is the careful planning,...
R. Baker & Son industrial contractors executing mission-critical transformer replacement with rigging equipment at medical facility
How R. Baker & Son Executes High-Stakes Projects with Engineered Work Plans

Mission-critical and high-stakes projects demand detailed, preplanned coordination to ensure success at every level. When it comes to plant shutdowns, startups, repairs, changeovers, and equipment...
R. Baker & Son rigging team performing final precision positioning and alignment of a multi-ton medical MRI magnet onto its concrete anchoring pad inside a specialized hospital imaging room.
MRI & Medical Imaging Equipment Rigging: A Turnkey Installation Case Study

Medical equipment rigging and installation requires a specialized approach to protect high-value, delicate assets. At R. Baker, we successfully navigate these complex rigging projects using...
R. Baker and son welding on complex hospital demolition job
Hospital Boiler Room Demolition: Removing Steam Boilers and Mechanical Equipment

R. Baker & Son was tasked with a complex demolition project at an active hospital, systematically removing two aging Cleaver-Brooks steam boilers (a 350 HP and a 200 HP unit), along with an...