All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Rigging and Setting the Final Pieces of Process Equipment

Rigging - Process Equipment

A large, ongoing pharmaceutical project was facing a dilemma. With most work progressing smoothly and on-schedule, equipment for one very important process area would not be arriving onsite until the very end of the project. R. Baker & Son and the construction manager came up with an ingenious plan for rigging the equipment into the facility without interrupting the flow of the project. 

R. Baker & Son had rigged and set in place various mechanical equipment including chillers, cooling towers, air handlers, heat exchangers, tanks, air compressors, and plumbing skids. Some of the process equipment arrived at the jobsite next and was routed through the corridors and into the process suites following a detailed rigging and routing plan developed early in the project. Process equipment included large isolators, tanks, servo lifts, filling lines and several large platforms. 

The process area in question was to include a two-story fluid bed, a granulator, and process air handling unit with control panel. All of the pieces were being fabricated and factory acceptance-tested before they were shipped from overseas. Because of the massive size of the equipment, R. Baker would not be able to bring it through the building, so it was decided that it would be rigged vertically through a exactly-plotted and -measured opening in the roof directly into the process suite onto pre-erected platforms where they would be mounted with precision. 

The final process equipment arrived three weeks from the completion date. All areas had been substantially finished, and finishing touches and punch list items were being completed. With a clear window of weather forecast, the temporary roof above the process suite was removed along with a section of ceiling fifteen feet below. The process air handling unit was rigged in on-end to fit through the opening, then turned to its horizontal position and set on its mechanical platform. Next, two Hoffman enclosure control panels were rigged onto the mechanical platform. The 1-ton, 8-ft. tall granulator came next, followed by the two-story vertical fluid bed weighing three tons, its feet mounted directly onto the awaiting stainless steel platform. 

Once the equipment had been set in place, the ceiling and roof openings were closed and sealed. Final electrical and mechanical interconnects were completed on the process equipment and air balancing was performed. The building was completed on time, and the project received its Certificate of Occupancy as scheduled.

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a  Service-Disabled Veteran-Owned Business (SDVOB)  in business since 1935, is a premier specialized contractor operating in the United States, Canada and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

https://rbaker.com

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Precision Chiller Dismantling & Mechanical Retrofit Case Study
Precision Chiller Dismantling & Mechanical Retrofit Case Study

A local New Jersey representative for a major chiller manufacturer recommended R. Baker & Son for a demanding chiller change-out project. The scope: remove two 1,200-ton chillers and their...
Discover how a custom negative pressure wall and real-time monitoring protected a pharmaceutical cleanroom during high-stakes facility demolition.
How to Protect Active Cleanrooms During Demolition: A Negative Pressure Wall Case Study

Protecting a client's environment during demolition and renovation work has always been part of what we do at R. Baker & Son. Anyone in the industry knows ICRA protection, the barrier system...
rigging medical equipment into a hospital - R. Baker & Son
Just-in-Time Rigging Keeps a Hospital Running During a Critical Enabling Project

R. Baker & Son received a call from a concerned South Jersey mechanical contractor facing a complex rigging project on a tight deadline. Another rigging contractor had passed on the job late in...
Riggers assembling tower crane sections during construction - R. Baker & Son - Master Riggers.
How Mobile and Tower Cranes Are Assembled & Dismantled

Mobile cranes come in many styles, shapes, and sizes, with the hydraulic crane and the luffing jib being the most common. R. Baker & Son has worked with just about every mobile crane on the...
Demolition concrete debris fed into an industrial crusher for recycling
7 Ways Demolition Protects Communities & the Planet

7 Ways Demolition Builds Better Communities -And Why It Matters When most people picture demolition, they see dust clouds and falling walls. What they don't see is the careful planning,...
R. Baker & Son industrial contractors executing mission-critical transformer replacement with rigging equipment at medical facility
How R. Baker & Son Executes High-Stakes Projects with Engineered Work Plans

Mission-critical and high-stakes projects demand detailed, preplanned coordination to ensure success at every level. When it comes to plant shutdowns, startups, repairs, changeovers, and equipment...
R. Baker & Son rigging team performing final precision positioning and alignment of a multi-ton medical MRI magnet onto its concrete anchoring pad inside a specialized hospital imaging room.
MRI & Medical Imaging Equipment Rigging: A Turnkey Installation Case Study

Medical equipment rigging and installation requires a specialized approach to protect high-value, delicate assets. At R. Baker, we successfully navigate these complex rigging projects using...
R. Baker and son welding on complex hospital demolition job
Hospital Boiler Room Demolition: Removing Steam Boilers and Mechanical Equipment

R. Baker & Son was tasked with a complex demolition project at an active hospital, systematically removing two aging Cleaver-Brooks steam boilers (a 350 HP and a 200 HP unit), along with an...