All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Accelerated Project Timelines with R. Baker BIM Laser Scans

R. Baker BIM Laser Scans for Demolition Project

R. Baker was awarded a large demolition project in an existing 130k sq/ft laboratory facility to make way for a new modern lab facility.  Our client had presented us with a very aggressive demolition schedule that was now six to seven weeks behind the original start date. This delay was due to a combination of items from permit approvals, unforeseen design delays, and final funding challenges. The project had specific construction milestones to be met to receive this critical funding. These delays could now put some of the early funding in jeopardy. About half of the project's demolition scope was select demolition in the mechanical, electrical, and laboratory areas. This was a significant concern for our client, and they were looking for ways to pull the schedule back. 


Our demolition approach needed to address the six-week start delay of the project. This would require cutting the demolition and construction start time by at least twenty-nine days. To do this, we knew the job needed intense planning, and all work had to be laid out in great detail beforehand to maximize efficiency for various crews working in multiple areas. Our response to this challenge was going to be a bit high-tech. We saw an opportunity to perform BIM laser scanning in many project areas. We then used the Bim 3-D models from the laser scans area by area. Going through the model in great detail, and bringing that information into the field we could carefully mark out and identify everything that needed to be removed and what would remain.

After careful planning and mark out using the BIM models, we were able to execute the demolition in a highly efficient manner. Before any demolition work began, all utilities were carefully cut, capped, and made safe. To further enhance efficiency, our demolition crews worked in a specific sequence of three. The first crew performed the actual demolition and removal, the second crew moved the debris to the loading docks, and the third crew loaded and placed the debris in the proper recycling dumpsters, and carefully placed equipment onto flatbeds, low boys, and waiting trucks for removal. 

Lastly, R. Baker removed most of the concrete housekeeping pads to save time while moving quickly through the facility. We also incorporated new construction needs by cutting openings in concrete floors and walls to accommodate new ductwork, mechanical and electrical utility piping. This allowed MEP installation contractors to begin their work much sooner per the schedule.

Through the upfront efforts of using BIM scanning technology, marking all work in detail, maximizing crew efficiency, and prepping for new work, we were able to bring the schedule back the needed six weeks, making for a very happy client. We also wanted to thank our client's facility and engineering crew, who greatly assisted in this effort. 

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a Minority and Women-Owned Business Enterprise (M/WBE), in business since 1935, is a premier specialized contractor operating in the United States, Canada, and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in six sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities of over $20 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

https://www.rbaker.com/selective-demolition.php

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Remote-controlled Brokk demolition machine performing precise concrete breaking on a high-risk construction job site.
How Remote Controlled Machinery Improves Demolition & Job Site Safety

According to OSHA, falls remain the number one safety issue on construction job sites. Struck-by incidents, electrocution, and caught-in or caught-between hazards round out what OSHA calls the Focus...
R. Baker & Son riggers setting water-cooled centrifugal chillers for data center cooling availability.
Data Center Rigging & MEP Installation: Keeping Projects on Schedule

Safe, efficient rigging and assembly of data center MEP systems starts with understanding how a data center operates. That means knowing what mechanical and electrical equipment is required, how each...
An 80-ton crane hoisting a new MRI machine during a medical equipment replacement project
Swapping an 8-Ton MRI in 48 Hours: Inside a Complex Medical Rigging Project

Six months after rigging two MRI machines, a CT scanner, a PET scanner, and their associated chillers and cooling equipment into a brand-new medical treatment facility, we got another call from the...
Precision Chiller Dismantling & Mechanical Retrofit Case Study
Precision Chiller Dismantling & Mechanical Retrofit Case Study

A local New Jersey representative for a major chiller manufacturer recommended R. Baker & Son for a demanding chiller change-out project. The scope: remove two 1,200-ton chillers and their...
Discover how a custom negative pressure wall and real-time monitoring protected a pharmaceutical cleanroom during high-stakes facility demolition.
How to Protect Active Cleanrooms During Demolition: A Negative Pressure Wall Case Study

Protecting a client's environment during demolition and renovation work has always been part of what we do at R. Baker & Son. Anyone in the industry knows ICRA protection, the barrier system...
rigging medical equipment into a hospital - R. Baker & Son
Just-in-Time Rigging Keeps a Hospital Running During a Critical Enabling Project

R. Baker & Son received a call from a concerned South Jersey mechanical contractor facing a complex rigging project on a tight deadline. Another rigging contractor had passed on the job late in...
Riggers assembling tower crane sections during construction - R. Baker & Son - Master Riggers.
How Mobile and Tower Cranes Are Assembled & Dismantled

Mobile cranes come in many styles, shapes, and sizes, with the hydraulic crane and the luffing jib being the most common. R. Baker & Son has worked with just about every mobile crane on the...
Demolition concrete debris fed into an industrial crusher for recycling
7 Ways Demolition Protects Communities & the Planet

7 Ways Demolition Builds Better Communities -And Why It Matters When most people picture demolition, they see dust clouds and falling walls. What they don't see is the careful planning,...