All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Accelerated Project Timelines with R. Baker BIM Laser Scans

R. Baker BIM Laser Scans for Demolition Project

R. Baker was awarded a large demolition project in an existing 130k sq/ft laboratory facility to make way for a new modern lab facility.  Our client had presented us with a very aggressive demolition schedule that was now six to seven weeks behind the original start date. This delay was due to a combination of items from permit approvals, unforeseen design delays, and final funding challenges. The project had specific construction milestones to be met to receive this critical funding. These delays could now put some of the early funding in jeopardy. About half of the project's demolition scope was select demolition in the mechanical, electrical, and laboratory areas. This was a significant concern for our client, and they were looking for ways to pull the schedule back. 


Our demolition approach needed to address the six-week start delay of the project. This would require cutting the demolition and construction start time by at least twenty-nine days. To do this, we knew the job needed intense planning, and all work had to be laid out in great detail beforehand to maximize efficiency for various crews working in multiple areas. Our response to this challenge was going to be a bit high-tech. We saw an opportunity to perform BIM laser scanning in many project areas. We then used the Bim 3-D models from the laser scans area by area. Going through the model in great detail, and bringing that information into the field we could carefully mark out and identify everything that needed to be removed and what would remain.

After careful planning and mark out using the BIM models, we were able to execute the demolition in a highly efficient manner. Before any demolition work began, all utilities were carefully cut, capped, and made safe. To further enhance efficiency, our demolition crews worked in a specific sequence of three. The first crew performed the actual demolition and removal, the second crew moved the debris to the loading docks, and the third crew loaded and placed the debris in the proper recycling dumpsters, and carefully placed equipment onto flatbeds, low boys, and waiting trucks for removal. 

Lastly, R. Baker removed most of the concrete housekeeping pads to save time while moving quickly through the facility. We also incorporated new construction needs by cutting openings in concrete floors and walls to accommodate new ductwork, mechanical and electrical utility piping. This allowed MEP installation contractors to begin their work much sooner per the schedule.

Through the upfront efforts of using BIM scanning technology, marking all work in detail, maximizing crew efficiency, and prepping for new work, we were able to bring the schedule back the needed six weeks, making for a very happy client. We also wanted to thank our client's facility and engineering crew, who greatly assisted in this effort. 

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a Minority and Women-Owned Business Enterprise (M/WBE), in business since 1935, is a premier specialized contractor operating in the United States, Canada, and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in six sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities of over $20 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

https://www.rbaker.com/selective-demolition.php

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

R. Baker & Son rigging team performing final precision positioning and alignment of a multi-ton medical MRI magnet onto its concrete anchoring pad inside a specialized hospital imaging room.
MRI & Medical Imaging Equipment Rigging: A Turnkey Installation Case Study

Medical equipment rigging and installation requires a specialized approach to protect high-value, delicate assets. At R. Baker, we successfully navigate these complex rigging projects using...
R. Baker and son welding on complex hospital demolition job
Hospital Boiler Room Demolition: Removing Steam Boilers and Mechanical Equipment

R. Baker & Son was tasked with a complex demolition project at an active hospital, systematically removing two aging Cleaver-Brooks steam boilers (a 350 HP and a 200 HP unit), along with an...
R. Baker & Son rigging team deploying specialized heavy-lift cranes and moving equipment to position critical backup power generators and electrical infrastructure at an enterprise data center.
Turnkey Data Center & Energy Infrastructure Rigging

The digital economy and the new energy economy are being built simultaneously, and both require moving extremely heavy, extremely expensive, and extremely sensitive equipment with zero margin for...
Custom 2,600 lb finishing beam aligned to an industrial dryer drum.
Industrial Drum Refinishing Support: A Custom Rigging and Structural Solution

When a manufacturer we had previously performed rigging assembly and installation work for returned more than a year later with a unique and complex challenge, they knew who to call. The company...
Air skates (air casters) lifting and moving multi-ton industrial equipment using compressed air in a plant relocation project
Air Skates: How to Move Multi Ton Loads Without Touching the Floor

Air skates, also known as air casters, air skids, or air dollies, are a specialized rigging solution that R. Baker & Son has deployed for many years to move heavy machinery, fragile equipment,...
demolition innovation in protection - substation, non metallic wire mesh,
Demolition Protection: Safeguarding People, Property & Critical Systems

What Demolition Protection Truly EntailsIn the complex world of demolition, protection goes far beyond basic safeguards. As therecognized leader in demolition protection, R. Baker & Son defines...
R. Baker & Son rigging crew performing pre-construction planning and heavy equipment rigging for demolition and industrial plant relocation project
Precon Services for Demolition, Rigging & Plant Relocation

For more than 90 years, R. Baker & Son has been delivering expert precon services for demolition, rigging, and industrial plant relocation projects. Before any construction work begins, our team...
Rigger working on R. Baker & Son - All Industrial Services. Welding.
Rigging, Assembly and BIM: Bridging the Gap

Prefabricated equipment and systems have become the standard for good reason. The more you can prefabricate, the faster, more cost-effective, and higher quality a project becomes. The goal is simple:...