Interior Demo: Mid-Project Changes Save Time and Money

Interior Demolition - Wet Saw

Discovering an opportunity for substantial cost savings during a project in progress is always a welcome surprise, which was the case on a warehouse renovation in which R. Baker & Son was tasked with performing the   of the 200,000 sq. ft. building. The building was to become a manufacturing plant with 10,000 square feet of offices occupying one corner and heavy mechanical areas throughout the facility. 

Phase one of the interior demolition project was fairly standard. After careful planning and coordination of utility shutoff, everything within the building’s four outer walls and roof were removed using equipment that included forklifts, loaders, and skid steers brought in through existing loading dock doors. R. Baker & Son also handled reclamation and resale of an existing generator and multiple transfer switches to help offset some of the demolition costs. 

The second phase of demolition was saw-cutting and removal of approximately 50,000 sq. ft. of the concrete floor slab to accommodate the new plant’s underground sanitary and process plumbing. It was during this time that it became clear that, with some careful planning and cutting of an addition 4,000 sq. ft. of slab by the Baker Team, much of the overhead electrical conduit and cable tray could be relocated below ground fairly easily, saving a considerable amount of money in labor and material. Not having racks of conduit suspended from the ceiling or cable tray with miscellaneous steel supports would also result in a much cleaner, more aesthetically-pleasing installation. 

R. Baker & Son worked closely with plumbing and electrical contractors throughout the BIM coordination process for precisely relocating, trenching and backfilling all pipe and conduit. These changes resulted in savings of $112,000 and four weeks were shaved from the overall master schedule. With a tight budget, aggressive schedule and cost overruns in other areas of the project, this was music to the owners’ ears.

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

R. Baker & Son rigging team performing final precision positioning and alignment of a multi-ton medical MRI magnet onto its concrete anchoring pad inside a specialized hospital imaging room.
MRI & Medical Imaging Equipment Rigging: A Turnkey Installation Case Study

Medical equipment rigging and installation requires a specialized approach to protect high-value, delicate assets. At R. Baker, we successfully navigate these complex rigging projects using...
R. Baker and son welding on complex hospital demolition job
Hospital Boiler Room Demolition: Removing Steam Boilers and Mechanical Equipment

R. Baker & Son was tasked with a complex demolition project at an active hospital, systematically removing two aging Cleaver-Brooks steam boilers (a 350 HP and a 200 HP unit), along with an...
R. Baker & Son rigging team deploying specialized heavy-lift cranes and moving equipment to position critical backup power generators and electrical infrastructure at an enterprise data center.
Turnkey Data Center & Energy Infrastructure Rigging

The digital economy and the new energy economy are being built simultaneously, and both require moving extremely heavy, extremely expensive, and extremely sensitive equipment with zero margin for...
Custom 2,600 lb finishing beam aligned to an industrial dryer drum.
Industrial Drum Refinishing Support: A Custom Rigging and Structural Solution

When a manufacturer we had previously performed rigging assembly and installation work for returned more than a year later with a unique and complex challenge, they knew who to call. The company...
Air skates (air casters) lifting and moving multi-ton industrial equipment using compressed air in a plant relocation project
Air Skates: How to Move Multi Ton Loads Without Touching the Floor

Air skates, also known as air casters, air skids, or air dollies, are a specialized rigging solution that R. Baker & Son has deployed for many years to move heavy machinery, fragile equipment,...
demolition innovation in protection - substation, non metallic wire mesh,
Demolition Protection: Safeguarding People, Property & Critical Systems

What Demolition Protection Truly EntailsIn the complex world of demolition, protection goes far beyond basic safeguards. As therecognized leader in demolition protection, R. Baker & Son defines...
R. Baker & Son rigging crew performing pre-construction planning and heavy equipment rigging for demolition and industrial plant relocation project
Precon Services for Demolition, Rigging & Plant Relocation

For more than 90 years, R. Baker & Son has been delivering expert precon services for demolition, rigging, and industrial plant relocation projects. Before any construction work begins, our team...
Rigger working on R. Baker & Son - All Industrial Services. Welding.
Rigging, Assembly and BIM: Bridging the Gap

Prefabricated equipment and systems have become the standard for good reason. The more you can prefabricate, the faster, more cost-effective, and higher quality a project becomes. The goal is simple:...