asset recovery, rigging team with sling and interior demolition

Interior Demo: Mid-Project Changes Save Time and Money

Interior Demolition - Wet Saw

Discovering an opportunity for substantial cost savings during a project in progress is always a welcome surprise, which was the case on a warehouse renovation in which R. Baker & Son was tasked with performing the   of the 200,000 sq. ft. building. The building was to become a manufacturing plant with 10,000 square feet of offices occupying one corner and heavy mechanical areas throughout the facility. 

Phase one of the interior demolition project was fairly standard. After careful planning and coordination of utility shutoff, everything within the building’s four outer walls and roof were removed using equipment that included forklifts, loaders, and skid steers brought in through existing loading dock doors. R. Baker & Son also handled reclamation and resale of an existing generator and multiple transfer switches to help offset some of the demolition costs. 

The second phase of demolition was saw-cutting and removal of approximately 50,000 sq. ft. of the concrete floor slab to accommodate the new plant’s underground sanitary and process plumbing. It was during this time that it became clear that, with some careful planning and cutting of an addition 4,000 sq. ft. of slab by the Baker Team, much of the overhead electrical conduit and cable tray could be relocated below ground fairly easily, saving a considerable amount of money in labor and material. Not having racks of conduit suspended from the ceiling or cable tray with miscellaneous steel supports would also result in a much cleaner, more aesthetically-pleasing installation. 

R. Baker & Son worked closely with plumbing and electrical contractors throughout the BIM coordination process for precisely relocating, trenching and backfilling all pipe and conduit. These changes resulted in savings of $112,000 and four weeks were shaved from the overall master schedule. With a tight budget, aggressive schedule and cost overruns in other areas of the project, this was music to the owners’ ears.

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Air skates (air casters) lifting and moving multi-ton industrial equipment using compressed air in a plant relocation project
Air Skates: How to Move Multi Ton Loads Without Touching the Floor

Air skates, also known as air casters, air skids, or air dollies, are a specialized rigging solution that R. Baker & Son has deployed for many years to move heavy machinery, fragile equipment,...
demolition innovation in protection - substation, non metallic wire mesh,
Demolition Protection: Safeguarding People, Property & Critical Systems

What Demolition Protection Truly EntailsIn the complex world of demolition, protection goes far beyond basic safeguards. As therecognized leader in demolition protection, R. Baker & Son defines...
R. Baker & Son rigging crew performing pre-construction planning and heavy equipment rigging for demolition and industrial plant relocation project
Precon Services for Demolition, Rigging & Plant Relocation

For more than 90 years, R. Baker & Son has been delivering expert precon services for demolition, rigging, and industrial plant relocation projects. Before any construction work begins, our team...
Rigger working on R. Baker & Son - All Industrial Services. Welding.
Rigging, Assembly and BIM: Bridging the Gap

Prefabricated equipment and systems have become the standard for good reason. The more you can prefabricate, the faster, more cost-effective, and higher quality a project becomes. The goal is simple:...
Several large steam-to-hot-water heat exchangers
Quick Mobilization for Pilot Plant Dismantling and Demolition

When a building consolidation commitment required our client to dismantle and demolish a 30,000 square-foot pilot plant immediately, they turned to R. Baker & Son. Having rigged much of the...
Rigging, completely assembling, and setting 12 large fiberglass cylindrical tanks, each with a 17,000-gallon capacity.
Rising to a Rigging Challenge: Tank Installation in N. Philadelphia

The Project Scope As part of a major rigging project in North Philadelphia, R. Baker & Son faced a complex installation challenge: rigging, completely assembling, and setting 12 large...
Nine downflow booths carefully dismantled and packaged for refurbishment during pharmaceutical lab renovation.
Negative Pressure Demolition in an Active Pharmaceutical R&D Laboratory

R. Baker & Son had the unique opportunity to return to a pharmaceutical R&D laboratory project we had successfully completed years earlier, where our riggers and millwrights originally...
Industrial building demolition with advanced machinery by R. Baker & Son
R. Baker & Son: Experts in Modern Demolition Technology

Building demolition technology has undergone remarkable transformations over the decades, reflecting advancements in engineering, safety standards, and environmental stewardship. The evolution from...