Rising to a Rigging Challenge: Tank Installation in N. Philadelphia

R. Baker & Son 80-ton crane lifting 17000-gallon fiberglass tank during North Philadelphia rigging installation

The Project Scope

As part of a major rigging project in North Philadelphia, R. Baker & Son faced a complex installation challenge: rigging, completely assembling, and setting 12 large fiberglass cylindrical tanks, each with a 17,000-gallon capacity. The tanks were to be delivered and anchored to waiting concrete pads in the rear of the facility. The agitators, blades, motors, and instruments shipped separately and would be assembled on site.

Coordinating Custom Equipment Delivery

The custom fiberglass tanks were fabricated and shipped on schedule from North Carolina, arriving on 12 separate wide-load tractor trailers. Each tank measured approximately 12 feet wide by 20 feet high, requiring careful logistics and planning for safe transportation and installation.

The tank agitators were custom-designed and fabricated to mix process slurry within the fiberglass tanks. These stainless steel agitators were manufactured in Alabama and shipped separately to the site. Due to the horizontal positioning of the tanks during transport and the risk of the agitators shifting in transit, the two components couldn't be shipped together. This meant the agitators and tanks would be assembled together for the first time on site, in a vertical position, in Philadelphia.

The Installation Process Begins

Once on site, R. Baker rigging crews deployed an 80-ton hydraulic crane with an extended jib to lift each tank into its vertical position directly from each tractor trailer in an assembly-line fashion at the building's large opening. The process appeared to be progressing smoothly—until a critical issue emerged.

A Show-Stopping Challenge

The problem became evident as crews lifted the 20-foot agitators with monolithic hubs to position them above and into the waiting tanks. The stainless steel hubs on the 4-inch stainless shaft were 1 inch too large to fit through the tanks' center top 16-inch reinforced flange. This was a complete show-stopper, preventing the agitators from being installed in the tanks and the tanks from being moved into the building.

Problem-Solving and Quick Action

Working collaboratively with the agitator manufacturer, R. Baker sent detailed photos with exact measurements to assess the issue. After careful analysis, the team agreed on a solution: remove or grind down corner sections of the agitator hubs to reduce the cross-sectional area, allowing the agitators to fit inside the tanks.

R. Baker immediately brought in a specialty stainless steel contractor the next morning to set up an on-site workspace. The contractor carefully ground down the hubs, rounded them, and polished them to like-new condition, ensuring both functionality and appearance were maintained.

Completing the Installation

As each 20-foot agitator shaft and hub was modified to fit properly, the R. Baker team assembled the agitators, 25-horsepower motors, and tanks together in sequence before moving them into the building in a safe and timely manner.

Once the tanks were transported from the front of the building to the rear and positioned on their pads, a second R. Baker team worked on centering each tank into its exact position and anchoring them with large epoxy anchors. After the tanks were securely set in place, crews mounted the agitator blades, baffles, and all associated instrumentation and lighting to complete the installation.

Successful Project Completion

Working in a coordinated sequence between various teams, R. Baker was able to complete the work on time, safely, and with quality results. Through effective collaboration with the client and vendors, the team successfully solved a problem that had stopped the project in its tracks and got everything back on schedule.

R. Baker & Son - Rigging & Demoliton Contractors
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

https://www.rbaker.com/rigging-contractors.php

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Discover how a custom negative pressure wall and real-time monitoring protected a pharmaceutical cleanroom during high-stakes facility demolition.
How to Protect Active Cleanrooms During Demolition: A Negative Pressure Wall Case Study

Protecting a client's environment during demolition and renovation work has always been part of what we do at R. Baker & Son. Anyone in the industry knows ICRA protection, the barrier system...
rigging medical equipment into a hospital - R. Baker & Son
Just-in-Time Rigging Keeps a Hospital Running During a Critical Enabling Project

R. Baker & Son received a call from a concerned South Jersey mechanical contractor facing a complex rigging project on a tight deadline. Another rigging contractor had passed on the job late in...
Riggers assembling tower crane sections during construction - R. Baker & Son - Master Riggers.
How Mobile and Tower Cranes Are Assembled & Dismantled

Mobile cranes come in many styles, shapes, and sizes, with the hydraulic crane and the luffing jib being the most common. R. Baker & Son has worked with just about every mobile crane on the...
Demolition concrete debris fed into an industrial crusher for recycling
7 Ways Demolition Protects Communities & the Planet

7 Ways Demolition Builds Better Communities -And Why It Matters When most people picture demolition, they see dust clouds and falling walls. What they don't see is the careful planning,...
R. Baker & Son industrial contractors executing mission-critical transformer replacement with rigging equipment at medical facility
How R. Baker & Son Executes High-Stakes Projects with Engineered Work Plans

Mission-critical and high-stakes projects demand detailed, preplanned coordination to ensure success at every level. When it comes to plant shutdowns, startups, repairs, changeovers, and equipment...
R. Baker & Son rigging team performing final precision positioning and alignment of a multi-ton medical MRI magnet onto its concrete anchoring pad inside a specialized hospital imaging room.
MRI & Medical Imaging Equipment Rigging: A Turnkey Installation Case Study

Medical equipment rigging and installation requires a specialized approach to protect high-value, delicate assets. At R. Baker, we successfully navigate these complex rigging projects using...
R. Baker and son welding on complex hospital demolition job
Hospital Boiler Room Demolition: Removing Steam Boilers and Mechanical Equipment

R. Baker & Son was tasked with a complex demolition project at an active hospital, systematically removing two aging Cleaver-Brooks steam boilers (a 350 HP and a 200 HP unit), along with an...
R. Baker & Son rigging team deploying specialized heavy-lift cranes and moving equipment to position critical backup power generators and electrical infrastructure at an enterprise data center.
Turnkey Data Center & Energy Infrastructure Rigging

The digital economy and the new energy economy are being built simultaneously, and both require moving extremely heavy, extremely expensive, and extremely sensitive equipment with zero margin for...